In negotiating construction contracts, few words can have greater financial consequences than “when,” “if,” and “unless.” Florida construction contracts commonly contain contingent payment clauses that govern when a general contractor must pay its subcontractors on private projects.
The Basic Difference
Florida law recognizes a critical distinction between two such clauses: a pay-if-paid clause, which operates as a true condition precedent that shifts the risk of the owner’s nonpayment to the subcontractor, and a pay-when-paid clause, which establishes a “reasonable time” for the general contractor to make a payment without eliminating their ultimate obligation to pay.
When a Pay-If-Paid Clause Actually Holds Up
The foundational rule when it comes to the pay-if-paid clause is that such a provision is enforceable only if the contract unambiguously expresses that payment to the general contractor is a condition precedent to payment, and clearly shows the intent to shift the risk of the owner’s nonpayment to the subcontractor. The burden of that clear expression falls on the general contractor. Any ambiguity in the contract is typically resolved by treating the clause as a pay-when-paid mechanism. To add another layer, depending on the specific terms, incorporation of a prime contract can also render such a clause ambiguous in certain circumstances. However, a properly drafted and enforceable pay-if-paid clause means that if an owner never pays a general contractor, the subcontractor is not entitled to payment from the general contractor.
How Pay-When-Paid Works – and a New 2026 Backstop
A pay-when-paid clause, by contrast, does not eliminate the general contractor's obligation to pay the subcontractor. Instead, it generally concerns the timing for the general contractor to make payment: typically, after the general contractor has received payment from the owner. Under Florida law, once the owner pays the general contractor (or once a reasonable time has passed), the general contractor's obligation to pay the subcontractor becomes due and enforceable. A pay-when-paid clause is generally the default interpretation in Florida when a payment provision is susceptible to more than one reasonable interpretation. Separately, effective July 1, 2026, Section 489.1295, Florida Statutes, requires a licensed contractor, unless there is a bona fide dispute regarding the amount due, to pay a subcontractor or supplier either within 45 days after receiving payment for the subcontractor’s or supplier’s services or materials, or in accordance with the terms of the contract. Note that the 45-day period runs from the contractor’s receipt of payment, not from completion or invoicing, and the statute is enforced through contractor licensing discipline for knowing and willful violations. It does not, on its face, override a contractual payment term or convert a valid pay-if-paid clause into an unconditional obligation to pay.
What the Courts Say: The Peacock Case
The Supreme Court of Florida addressed this exact scenario in Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc., 353 So. 2d 840 (Fla. 1977) In this case, the court evaluated a contract clause that provided the general contractor would make payment “within 30 days after completion of the work included in this sub-contract, written acceptance by the Architect and full payment therefor by the Owner.” The court found that the provision could be interpreted either as setting a condition precedent or as fixing a reasonable time for payment. Because the provision did not unambiguously express the intention to shift the burden of nonpayment to the subcontractor, it was interpreted as a pay-when-paid clause in favor of the subcontractor. Subsequent Florida cases have applied and interpreted Peacock in addressing whether contractual payment provisions clearly establish a condition precedent or instead merely establish the timing of payment.
The Lien Rights Wrinkle
The distinction can become even more complex when lien rights are involved. Florida’s public policy protections concerning construction lien rights can limit the effect that contractual payment provisions may have on those rights. A valid pay-if-paid clause can bar a subcontractor’s breach-of-contract claim against the general contractor, but it does not by itself extinguish the subcontractor’s separate right to record a construction lien, since Florida law does not allow lien rights to be waived in advance. That said, the lien remains available only if the subcontractor satisfies the notice, timing, and other requirements of Florida’s Construction Lien Law, so a pay-if-paid clause does not guarantee recovery through the lien process. Accordingly, the enforceability and effect of a pay-if-paid or pay-when-paid provision may require consideration not only of contract language, but also of the statutory and public policy protections applicable to construction lien rights.
The difference between “when” and “if” can determine whether an unpaid subcontractor is waiting for payment or waiting indefinitely for a payment obligation that the contractor contends never arose.
The Takeaway
In negotiating and reviewing contracts, do not rely on labels. Read the entire contract and identify the intended allocation of risk. It is critical to understand who ultimately absorbs the loss when an owner does not pay – and, as of July 1, 2026, whether your subcontract specifies payment timing at all, now that Section 489.1295 requires payment within 45 days after the contractor receives payment for the work, unless the contract provides otherwise or there is a bona fide dispute over the amount due.
Having a construction attorney review the contract can help identify payment provisions, potential risk-shifting language, and other issues that may affect your rights and obligations before a dispute arises.
Questions?
Contact GrayRobinson Senior Associate Michele A. Ebone or a member of the Construction Team.